Power Play | Episode 3 | Defending Defects

Osborne Clarke.TV Podcasts15mApril 9, 2026

Get the full intelligence

Search transcripts, export clips, track mentions, and explore all topics from “Power Play | Episode 3 | Defending Defects” inside PodZeus.

AI-Generated Summary

In this episode of the Powerplay podcast, Dan Cashmore and Danielle Griffiths explore the critical issue of defects and performance issues in renewable energy assets, emphasizing their impact on project value, regulatory compliance, and safety. The discussion covers the lifecycle stages—construction, commissioning, and operation—where defects can emerge, and how contractual frameworks govern the identification, notification, and resolution of these issues. Key topics include the importance of defect liability periods, the distinction between construction-phase and post-completion defects, and the legal and commercial implications of failing to properly notify or address defects. The hosts stress the necessity of early technical and legal intervention, proper notice compliance, and protecting contractual rights throughout investigations. They also highlight the role of performance testing, liquidated damages, expert determination, and limitation periods in managing disputes. The episode concludes with actionable takeaways: strictly adhere to notice provisions, seek technical and legal advice early, preserve all rights during investigations, and consider expert determination to resolve deadlocks. The overall tone is constructive and practical, offering clear guidance for asset owners and operators navigating the complexities of renewable infrastructure risks. The episode underscores the importance of balancing commercial urgency with contractual diligence to safeguard long-term asset performance and financial viability.

Key Takeaways
1

Always comply strictly with notice provisions in contracts to preserve defect claims.

2

Engage technical experts early to identify root causes and assign responsibility for defects.

3

Protect all contractual rights during investigations by putting relevant parties and insurers on notice.

4

Be cautious about issuing final acceptance certificates if known defects remain unresolved.

5

Leverage expert determination to break deadlocks on performance or defect disputes.

…and 3 more takeaways available in PodZeus

Chapters
0:00
2 min

Introduction to Defects in Renewable Assets

Dan Cashmore introduces the episode's focus on defects in renewable energy assets, setting the stage for a discussion on risk management throughout the asset lifecycle from a legal and commercial perspective.

2:25
3 min

Defining Defects and Their Financial Impact

Danielle Griffiths defines defects in the context of renewable assets, explaining how they affect performance, revenue, regulatory compliance, and safety, and why asset owners must prioritize their resolution.

5:20
5 min

Defects During Construction and the Liability Period

It's kind of useful, but I'd say critical to ensure that a full review of any potential defects is carried out before the end of that defects liability period to ensure there's enough time to notify everything that needs to be fixed.

Highlight
10:00
4 min

Latent Defects and Post-Warranty Remedies

If a contractor doesn't come back and fix a defect that's identified outside of a defect liability period, the employer or owner's recourse is to have that defect rectified by a third party and then to seek to recover the cost of doing so as damages from the contractor.

Highlight
14:10
1 min

Performance Testing, Acceptance, and Final Tips

Early legal involvement can really be the difference between making good a defects claim or not.

Highlight
High-Impact Quotes
Early legal involvement can really be the difference between making good a defects claim or not.
Dan Cashmore14:13
Viral: 85.0
If a contractor doesn't come back and fix a defect that's identified outside of a defect liability period, the employer or owner's recourse is to have that defect rectified by a third party and then to seek to recover the cost of doing so as damages from the contractor.
Danielle Griffiths8:40
Viral: 82.0
It's kind of useful, but I'd say critical to ensure that a full review of any potential defects is carried out before the end of that defects liability period to ensure there's enough time to notify everything that needs to be fixed.
Danielle Griffiths7:27
Viral: 78.0
Speakers

Host

Dan Cashmore

Guest

Danielle Griffiths
Topics Discussed
Defects in Renewable Energy Assets95%Defect Liability Periods90%Performance Testing and Commissioning85%Contractual Notice Requirements80%Latent Defect Claims75%Liquidated Damages70%Expert Determination65%Asset Lifecycle Risk Management60%
People & Brands

Danielle Griffiths

person

15xPositive

Dan Cashmore

person

12xNeutral

Defect Liability Period

other

6xNeutral

Liquidated Damages

other

4xNeutral

EPC Contractor

organization

3xNeutral

Final Acceptance Certificate

other

3xNegative

Expert Determination

other

3xPositive

O&M Contractor

organization

2xNeutral

Osborne Clarke

organization

2xPositive

Statutory Limitation Period

other

2xNeutral

Get the full intelligence

Search transcripts, export clips, track mentions, and explore all topics from “Power Play | Episode 3 | Defending Defects” inside PodZeus.

Start discovering podcast insights today

Start with a 7-day trial and explore a growing catalog of popular podcasts. No credit card required.

No credit card required • 7-day trial • Cancel anytime